Click on an image to enlarge
October 2007


The first loading of Apatite from
the Goondicum Wet Separation Plant
______________________________________________________

 
   Feldspar Upgrading Plant   /  The Drying Floor

Lining the Reactor  /  Railway load out conveyor
______________________________________________________
August 2007

Testing the Water Cannon at Goondicum

Wet Plant and Thickener

De-sliming Cyclones and Ilmenite Spirals

Feed Preparation Plant

Feldspar and Apatite Section / Tables

Feldspar Feed WHIMS       /   Ilmenite WHIMS & Spirals

Sump and Feed Preparation Plant

Water Cannon and Ore Stockpile
 
Thickener and Process Water Dam
______________________________________________________
 10 July 2007

Feed Prep Area  /  Wet Separation Plant / Spirals & Magnets


______________________________________________________
27 June 2007
Directors meet the Goondicum Shift Supervisors
during their Safety Course

First day of water pumping into Dam

Continuing Construction at the Goondicum Wet Plant
 

 
  ______________________________________________________
30 May 2007
Early morning at the Goondicum Wet Plant
 

 Continuing Construction at the Goondicum Wet Plant


Early May - Work continues at the Goondicum Wet Plant


______________________________________________________
April 2007
Work continues on the construction of the
Goondicum Wet Plant

Progress on the dam at Dakiel. In the final photo the dam has 110,000 litres of water in it.



The Rail Trial for transportation of Ilmenite and Feldspar
from Monto to Gladstone Port.

The train makes it ways through Kalpower,
on its way from Monto to Gladstone Port.

March 2007
Construction work progresses.

 

 

Operations Manager, Phil McMurtrie inspects the bore drilling work that will provide water to the mine site.


High Grade Mineral Zones at Goondicum.


Work continues on the construction of the Goondicum Wet Plant

     


   

Cattle wander across the construction area.
 
Erecting the Structural Steel at Goondicum Wet Plant

   

Construction of the Thickener at Goondicum Wet Plant

January 2007
Construction of Storage Shed


November 2006
Concrete Pour for Goondicum
Wet Plant

Bags of titanomagnetite
for Commercial Testing

Mine Access Road works

Monto Shire Road works

September 2006
Goondicum Plant Earthworks

Process Water Storage Dam

Overview of Progress
at Goondicum Project Site
                
29 August 2006
Goondicum initial site
works continue
   
24 August 2006
Goondicum Project Wet Plant Pad

Goondicum Project dam wall.
Goondicum Project dam site
Goondicum Project access road.
October 2004
First production bottle from ACI Glass using Monto Feldspar.